Case Study

Case Study: Hangar Roof Insulation | Alton, Hampshire

Alton, Hampshire, England Aircraft Hangar
System used
Enverge Nexseal LE (25mm) & Sucraseal (150–200mm)
Roof / substrate area
4,000m²
Programme
3 Weeks
4,000
Roof / substrate area
3 weeks
On-site programme
The Transformation

From failing roof to finished system

BeforeOf Black Hangar Studios
ApplicationTo Show Sucraseal Open Cell Spray Foam Insulation Being Applied Onto A Nexseal LE Closed Cell Spray Foam Base Layer For Hangar Roof Insulation
FinishedTo Show Spray Foam Insulation Used For Hangar Insulation
Act One

The Challenge

Black Hangar Studios in Alton, Hampshire, is home to major film productions including Dumbo, Salmon Fishing in the Yemen and Live Another Day. The large 4,000m² aircraft hangar used as a main sound stage was suffering from excessive noise from the corrugated asbestos/cement fibre roof during high winds and rainfall. The constant drumming and resonance from the roof sheets made sound recording difficult and disrupted filming schedules.

Duratite were tasked with specifying a roof insulation system that would strengthen the roof structure and eliminate the noise problems caused by weather impact.

Challenge

The hangar’s ageing asbestos/cement fibre roof was fragile and prone to vibration, generating a loud echo throughout the internal space. The sheer size of the roof area meant any solution had to provide:

  • Structural reinforcement to prevent panel movement in strong winds.
  • Sound attenuation to absorb rain impact noise.
  • Thermal insulation to stabilise internal temperatures.
  • Full compliance with British fire performance standards.

The work also needed to be carried out safely and efficiently, with minimal disruption to studio operations.

To Show Warehouse Hangar Ready For Hangar Insulation

Project file

Building typeAircraft Hangar
LocationAlton, Hampshire, England
ClientBlack Hangar Studios
Area4,000 m²
SystemNexseal LE + Sucraseal
Thickness25mm + 150–200mm
InstallerBritish Insulation Services & Spray Foam Tech
Of The Nexseal And Sucraseal Spray Foam Insulation System For Warehouse Insulation
Roof like this one?

Book a free survey and we’ll come back with a fixed price for your own roof.

Act Two

The Solution — step by step

1

Specification

Duratite specified a dual-foam insulation system combining the structural and acoustic benefits of two Enverge spray foams:

  • 25mm Enverge Nexseal LE Closed-Cell Foam
    • Sprayed directly onto the corrugated asbestos/cement fibre roof.
    • Formed a tough, bonded layer that sealed the substrate and improved rigidity.
    • Added resistance against vibration and movement under wind load.
    • Provided a continuous moisture-resistant membrane and improved base thermal value.
  • 150–200mm Enverge Sucraseal Open-Cell Foam
    • Applied beneath the closed-cell layer to form a thick acoustic and thermal barrier.
    • Greatly reduced external noise from rain and wind.
    • Delivered high breathability and excellent sound absorption.
    • Achieved British Class 1 Surface Spread of Flame fire performance rating.

This combination created a reinforced composite system — structurally sound, thermally efficient, and acoustically stable for film recording.

Enverge Nexseal LE Enverge Sucraseal
2

Installation

The insulation works were completed by Duratite-approved contractors British Insulation Services and Spray Foam Tech over three weeks in April 2021.

  • Full scissor lift access was utilised to reach all roof spans safely.
  • Controlled spraying methods were used to ensure no disturbance to the asbestos/cement substrate.
  • The Nexseal LE base layer was applied first to seal and stabilise the roof sheets.
  • Sucraseal open-cell foam was then sprayed in multiple passes to achieve the target 150–200mm depth.
  • Final inspection confirmed uniform coverage, adhesion, and finish across the 4,000m² roof area.
Enverge Nexseal LE Enverge Sucraseal
Act Three

The Outcome

The completed system provided immediate acoustic improvement. The drumming and resonance from rain and wind were virtually eliminated, transforming the hangar into a quiet, controlled environment ideal for high-quality film and audio production.

Key outcomes included:

  • Significant reduction in noise transmission from the roof.
  • Improved structural stability and vibration resistance.
  • Enhanced thermal performance and internal comfort.
  • Fully compliant fire performance and material safety.

Black Hangar Studios now benefits from a long-term warehouse insulation solution that strengthens the roof, controls sound intrusion, and supports ongoing film production without disruption.

Noise reductionCondensation eliminatedThermal performance
Installed by British Insulation Services & Spray Foam Tech — a Duratite-approved installer.
Free Survey · Fixed Price

Have a similar hangar insulation project?

Tell us about the building and the roof, send a few photos, and we’ll book a free survey and come back with a fixed price — the same process that delivered this project.

Prefer to talk it through?

Speak to a specialist about your project — no obligation, no hard sell.

info@duratite.ie · Mon–Fri, 8am–5pm
Free Site Survey

Get a Free Site Survey & Quote

Tell us about your building and we’ll recommend the right system — foam, waterproofing or both — surveyed, specified and quoted at no cost.

  • Reviewed by a Duratite specialist
  • No obligation, no hard sell
  • One team from survey to warranty
  • Ireland and Northern Ireland coverage
info@duratite.ie
No obligation · We’ll never sell your details · Typical reply within 1 working day
0 0.00
Email a Duratite expert info@duratite.ie